Safe Two-Lane Highway 12 NOW Coalition Records, 1988-1997


Summary Information
Title: Safe Two-Lane Highway 12 NOW Coalition Records
Inclusive Dates: 1988-1997

Creator:
  • Safe Two-Lane Highway 12 NOW Coalition
Call Number: M2001-104; Audio 1914A

Quantity: 2.8 cubic feet (2 records center cartons and 2 archives boxes) and 1 tape recording

Repository:
Archival Locations:
Wisconsin Historical Society (Map)

Abstract:
Records, 1988-1997, documenting the controversial decision by the Wisconsin Department of Transportation (WisDOT) to expand US Highway 12 to four lanes between Middleton and Lake Delton and the efforts by citizens and environmental groups to oppose such an enlargement. The records primarily document the efforts of the Safe Two-Lane Highway 12 NOW Coalition, but also include supporting documentation compiled by the coalition such as government documents detailing the growth of the project, and news clippings about the conflict.

Language: English

URL to cite for this finding aid: http://digital.library.wisc.edu/1711.dl/wiarchives.uw-whs-m2001104
 ↑ Bookmark this ↑

Scope and Content Note

The records are arranged in three series: SAFE TW0-LANE HIGHWAY 12 NOW COALITION, GOVERNMENT DOCUMENTS, and AUDIO RECORDING. The SAFE TW0-LANE HIGHWAY 12 NOW COALITION series documents the efforts of the coalition to maintain Highway 12 as a two-lane highway while making substantial safety improvements, instead of enlarging it to four-lanes. These records consist of correspondence, publicity materials, activities of the coalition, and research files compiled for possible legal challenges to the construction.

The GOVERNMENT DOCUMENTS series consists of the records of Ayres and Associates, the engineering firm the state hired to study the enlargement of the highway, and include correspondence, memos, a Highway 12 newsletter published jointly with WisDOT, and the minutes and agendas for Ayres's monthly meetings. Also included are WisDOT's environmental impact statements (EIS) and comments on these reports by the Coalition and other government and private groups as well as local government resolutions and transportation and land use plans for cities and counties located in the construction corridor. Additionally there are records obtained by Roads with Reason (a local environmental group) through an Open Records request in 1993 which contain correspondence, memos, and reports from WisDOT, Ayres, and other state agencies regarding Highway 12 construction from 1988 to 1993, the first five years of the project.

Administrative/Restriction Information
Acquisition Information

Presented by 1000 Friends of Wisconsin Inc., Madison, Wisconsin. Accession Number: M2001-104


Contents List
M2001-104
Series: Safe Two-Lane Highway 12 Now Coalition
Box   1
Folder   1
Mission statement
Box   1
Folder   2
Leaders
Box   1
Folder   3-10
Correspondence
Box   1
Folder   11
Memos
Box   1
Folder   12
Notes
Box   1
Folder   13
Flyers, mailings, and information sheets
Box   1
Folder   14
Newsletter
Box   1
Folder   15
Presentation materials
Box   1
Folder   16
Meeting minutes
Box   1
Folder   17
Northwest Chapter
Box   1
Folder   18
List of farmer and business coalition supporters along Highway 12
Box   1
Folder   19
Baraboo activities
Box   1
Folder   20
Middleton activities
Box   1
Folder   21
Sauk Prairie activities
Box   1
Folder   22-25
Groups supporting the coalition
Box   1
Folder   26
Legal issues file
Box   1
Folder   27
Maps
Box   1
Folder   28
Bad faith claims
Box   1
Folder   29-30
Badger ammunition plant
Box   1
Folder   31-35
Baraboo Hills
Box   1
Folder   36-39
Endangered species
Box   1
Folder   40
Energy statute
Box   1
Folder   41
Historic preservation concerns
Box   1
Folder   42
Federal Intermodal Surface Transportation Efficiency Act (ISTEA)
Box   1
Folder   43-44
Land Use
Box   1
Folder   45
Roads with Reason investigations
Box   1
Folder   46-47
Segmentation issues
Box   1
Folder   48
Trails/Road conflicts
Box   1
Folder   49
Wetlands
Box   4
Folder   3-4
Newspaper clippings
Series: Government Documents
Ayres Associates Files
Box   1
Folder   50-51
Correspondence and memos
Box   1
Folder   52
Ayres contacts with Army Corps of Engineers
Box   1
Folder   53
Ayres contacts with the EPA
Box   1
Folder   54
Ayres contracts
Box   1
Folder   55-56
Monthly meetings and minutes
Box   1
Folder   57
US Highway 12 newsletter
Environmental Impact Statements (EIS)
Box   2
Folder   1
Wisconsin Department of Transportation (WisDOT) EIS position paper
Box   2
Folder   2-3
Pre Draft EIS (DEIS) comments and meetings
Box   2
Folder   4
Pre-DEIS hearings
Box   2
Folder   5
Comments on DEIS
Box   2
Folder   6
WisDOT work plan on Supplemental EIS (SEIS)
Box   2
Folder   7
SEIS comments
Box   2
Folder   8
Baraboo Hills SEIS comments
Box   2
Folder   9
Walter Kulash/Coalition SEIS response
Box   2
Folder   10
SEIS partial
Box   2
Folder   11
EIS report appendices
Local Government Activities
Box   2
Folder   12
Local government resolutions
Box   2
Folder   13-17
Dane County
Box   2
Folder   18
Town of Dane
Box   2
Folder   19
Middleton
Box   2
Folder   20
Roxbury
Box   2
Folder   21
Sauk Prairie
Box   2
Folder   22
Sauk County
Box   2
Folder   23
Springfield
Open Records Act Documents
Box   2
Folder   24
Open Records Requests
Box   2
Folder   25
Cost documents
Box   2
Folder   26
Environment documents
Box   2
Folder   27
Land use and economic development documents
Box   2
Folder   28
Safety and accident rates documents
Box   2
Folder   29
Sauk City bypass documents
Box   2
Folder   30-38
Documents by date, 1988-1993
WisDOT Documents
Box   3
Folder   1
Correspondence and memos
Box   3
Folder   2
Project statements and information sheets
Box   3
Folder   3
Interagency meeting, January 1995
Box   3
Folder   4
Transportation projects commission
Box   3
Folder   5
Sauk City to Middleton commutershed study, January 1996
Box   3
Folder   6
Agricultural impact statement, October 1994
Box   3
Folder   7
Environmental review proposal
Box   3
Folder   8-9
Highway 12 study committee report
Box   3
Folder   10
Highway 12 accident data
Box   3
Folder   11
Safety
Box   3
Folder   12
Project cost estimations
Box   3
Folder   13
I 90-94 to Ski Hi Road project papers
Box   3
Folder   14
Sauk City bypass
Box   3
Folder   15
Middleton bypass
Box   3
Folder   16-18
Public hearings
Box   4
Folder   1-2
Citizen comments and letters
1914A/1
Series: Audio Recording